【摘 要】趙口灌區(qū)是河南省大(Ⅰ)型引黃灌區(qū)之一,位于河南省鄭州市中牟縣。近年來灌區(qū)進(jìn)行續(xù)建配套與節(jié)水改造工程項(xiàng)目,使老引黃灌區(qū),煥發(fā)了新的生命力,本文以灌區(qū)渠道改造襯砌混凝土施工為主線從施工單位進(jìn)場(chǎng)、測(cè)量、報(bào)方案、試驗(yàn)等施工準(zhǔn)備工作入手,闡述了灌區(qū)渠道施工的特點(diǎn)應(yīng)注意的一些事項(xiàng)等問題。
【關(guān)鍵詞】灌區(qū)渠道襯砌;碾壓試驗(yàn);含水率;密實(shí)度
【Abstract】Zhaokou Irrigation District is one of the large (I) type Yellow River irrigation areas in Henan Province, located in Zhongyu County, Zhengzhou City, Henan Province. In recent years, the irrigation district has continued to build supporting and water-saving renovation projects, which has brought new vitality to the old Yellow River Irrigation District. This paper uses the irrigation district to transform the lining concrete construction as the main line from the construction unit to enter, measure, report plans, test and other construction. Prepare the work and explain some issues that should be paid attention to in the characteristics of the channel construction in the irrigation district.
【Key words】Irrigation zone channel lining;Rolling test;Water content;Compactness
趙口灌區(qū)是河南省大(Ⅰ)型引黃灌區(qū)之一,位于河南省鄭州市中牟縣。設(shè)計(jì)引水流量150m3/s,規(guī)劃灌溉面積590.1萬畝,受益范圍涉及鄭州、開封、許昌、周口、商丘等五市的15個(gè)縣(區(qū))。
1. 工程主要內(nèi)容包括:渠道襯砌,泥結(jié)碎石道路、混凝土道路、橋梁、口門、分水閘、節(jié)制閘、綠化等工程。本文就渠道襯砌施工談幾點(diǎn)建議。
1.1 施工控制網(wǎng)和河道、建筑物的放線定位是設(shè)計(jì)要求的關(guān)鍵。
(1)施工控制網(wǎng)和測(cè)量放線出現(xiàn)偏差,將會(huì)給工程造成較大的損失,給后期的結(jié)算帶來糾紛。測(cè)量成果應(yīng)有建管、監(jiān)理、施工單位三方人員復(fù)測(cè)并簽字后,方可進(jìn)行施工,及時(shí)對(duì)比實(shí)際工程量和招標(biāo)文件工程量,如果差別較大要及時(shí)向建管單位提出,以便進(jìn)行投資控制。
(2)趙口灌區(qū)改造的特點(diǎn)是工期短,占線長,施工內(nèi)容多,應(yīng)統(tǒng)籌兼顧合理安排施工。春秋兩季為了保證農(nóng)業(yè)灌溉用水,渠道引水是不會(huì)停止的,一直處于運(yùn)行狀態(tài);施工期一般安排在當(dāng)年的十一、十二月或者次年的四、五月份暫停引水空檔進(jìn)行施工。
1.2 施工單位進(jìn)駐施工現(xiàn)場(chǎng)后首先要進(jìn)行渠道縱斷面、橫斷面測(cè)量,人員、機(jī)械進(jìn)場(chǎng)登記、申報(bào)施工組織設(shè)計(jì)及施工專項(xiàng)方案如排水、圍堰等施工方案。進(jìn)行原材料的篩選和檢驗(yàn),混凝土配合比試驗(yàn),土方碾壓試驗(yàn)等工作。
1.3 施工前的準(zhǔn)備工作大約需要二十天左右,如果是當(dāng)年開工的已進(jìn)入冬季,要提前做好冬季施工的準(zhǔn)備,選擇上午十點(diǎn)后至下午五點(diǎn)前施工,增加混凝土的覆蓋保溫等工作。如果是次年開工,已進(jìn)入夏季,這個(gè)時(shí)段不利于渠道薄壁混凝土襯砌施工,應(yīng)該避高溫、在施工現(xiàn)場(chǎng)適時(shí)灑水增加濕度,改善施工環(huán)境等措施。施工時(shí)段應(yīng)選擇在早晨六點(diǎn)到十點(diǎn)、下午四點(diǎn)到七點(diǎn)施工。
1.4 渠道混凝土襯砌施工占線長、工作量大是施工的關(guān)鍵線路,應(yīng)組織多個(gè)作業(yè)隊(duì)分段進(jìn)行施工。灌區(qū)改造施工內(nèi)容多,有渠道襯砌、渠系建筑物、橋梁、堤頂?shù)缆返裙こ?,?yīng)該合理安排施工順序,平行、穿插相結(jié)合,避開交叉施工。
2. 施工質(zhì)量控制的重點(diǎn)和難點(diǎn)
2.1 原材料和中間產(chǎn)品的質(zhì)量控制問題。由于渠道混凝土襯砌有多個(gè)作業(yè)隊(duì)分段施工,有條件的施工單位自建拌和站,混凝土質(zhì)量比較好控制,但是多數(shù)的施工單位采用商品混凝土,難以從源頭上控制混凝土質(zhì)量,為減少商混產(chǎn)品的不穩(wěn)定性,建議施工單位對(duì)所采購混凝土提高一個(gè)標(biāo)號(hào),在施工過程中多抽取試件并及時(shí)試驗(yàn),隨時(shí)跟蹤、控制商品混凝土的質(zhì)量。
2.2 土方密實(shí)度質(zhì)量的控制。趙口灌區(qū)渠道長時(shí)間受黃河水的沖刷和淤積,局部扭曲,需裁彎取直,以保證水流的順暢。要對(duì)回填部位高度重視,對(duì)填筑方案認(rèn)真審查,做好碾壓試驗(yàn),控制好土料的含水率以及鋪土厚度、碾壓遍數(shù)和結(jié)合部位的處理,襯砌前要對(duì)基面進(jìn)行質(zhì)量驗(yàn)收。
2.3 渠道周邊土壤多為砂壤土,土壤密實(shí)要求土壤含水率要大,一般在13%左右。渠道基面清理與襯砌混凝土施工時(shí)間間隔越短越好,基面能保持較多的土壤水分,特別是襯砌基面在混凝土鋪設(shè)前一定要灑水、平整,保證基面的密實(shí)度和混凝土襯砌厚度符合設(shè)計(jì)要求,減少后期襯砌面板斷裂情況的發(fā)生。
2.4 渠道混凝土襯砌面板的質(zhì)量控制,在不同的季節(jié)對(duì)混凝土塌落度要求不一樣,冬季由于蒸發(fā)量小,塌落度可以小一兩個(gè)數(shù)值,夏季則可以增加一兩個(gè)數(shù)值。
2.5 坡面混凝土的振搗要由下至上、均勻一致,既要振搗充分又不能過振使表面浮漿過多,延長收面時(shí)間或致表面龜裂;邊角和齒槽不宜振到位的可用5cm的小振搗棒補(bǔ)振一遍,然后用振動(dòng)梁復(fù)振一遍;表面平整后等待收面時(shí)機(jī),磨光機(jī)配合人工收面,表面終凝前用地膜覆蓋保持溫潤,以后可以根據(jù)天氣和氣溫情況適時(shí)進(jìn)行灑水養(yǎng)護(hù)。
2.6 襯砌面板間的伸縮縫安裝質(zhì)量對(duì)混凝土面板的外觀質(zhì)量影響較大,伸縮縫采用閉孔泡沫板,按設(shè)計(jì)要求的尺寸采購。澆筑混凝土前要在模板上用細(xì)鐵絲固定,使其在振搗過程中不會(huì)上浮移動(dòng)或變形,在收面后要人工清除伸縮縫上的浮漿,減少后期的漲裂??傊刂坪没炷恋乃涠?、初凝時(shí)間、振搗質(zhì)量和收面養(yǎng)護(hù)等幾個(gè)關(guān)鍵步驟。
3. 施工環(huán)境
3.1 渠道工程占線長,要抓好渠道暫停引水灌溉的空檔,加快施工進(jìn)度,加大與地方的協(xié)調(diào)力度減少施工期間的人為干擾。
3.2 施工降排水 在渠道施工中常遇到周邊種植水稻、有漁塘滲流等情況,導(dǎo)致地下水位較高,無法施工。施工中采用輕型井點(diǎn)降水;也可采用在渠底兩側(cè)挖排水溝的方法排水。這兩種方法很好的解決了施工中降排水問題。
4. 工程計(jì)量、進(jìn)度款支付未經(jīng)質(zhì)量評(píng)定合格的項(xiàng)目不允許簽證支付。加大對(duì)索賠、變更事件的預(yù)測(cè)防范,嚴(yán)格控制工程造價(jià)在工程建設(shè)合同價(jià)范圍內(nèi)。
5. 安全生產(chǎn)
本工程施工有高空作業(yè),大型機(jī)械作業(yè),交叉作業(yè),高邊坡作業(yè),施工用電和工區(qū)交通等情況,要加強(qiáng)施工人員的崗前培訓(xùn)和安全意識(shí)教育。對(duì)一些危險(xiǎn)性較大的工程如橋梁吊裝,要制定有效的安全防護(hù)措施,上報(bào)橋梁吊裝專項(xiàng)方案;建立施工、監(jiān)理、建管多級(jí)隱患排查體系,以及季節(jié)性,節(jié)假日,重要作業(yè)期等特殊時(shí)段的專項(xiàng)安全檢查,定期或不定期組織安全生產(chǎn)專題會(huì)議,對(duì)安全生產(chǎn)檢查情況進(jìn)行分析、總結(jié),提高參建各方的安全生產(chǎn)意識(shí)。
6. 結(jié)語 按規(guī)范、合同規(guī)定行使職責(zé)和權(quán)利,保證施工的分工協(xié)作,相互配合,使施工管理工作保持良性循環(huán)的狀態(tài)。灌區(qū)續(xù)建配套年度工程一般為正在運(yùn)行的灌區(qū),分年度逐步實(shí)施,工程施工不同程度受施工環(huán)境、天氣時(shí)段等多方面的影響,又面臨工程實(shí)施與灌區(qū)引水相沖突的矛盾。工程施工合同有效工期短、施工質(zhì)量要求高是續(xù)建配套年度工程特點(diǎn),因此,優(yōu)選信譽(yù)、業(yè)績(jī)好,施工組織能力強(qiáng),管理水平高的施工隊(duì)伍,是建設(shè)項(xiàng)目順利實(shí)施的關(guān)鍵。
[文章編號(hào)]1619-2737(2018)05-28-863
[作者簡(jiǎn)介] 崔洪濤(1969.4-),男,籍貫:河南鄭州,職稱:高級(jí)工程師,從事水利建設(shè)工程的監(jiān)理工作二十多年,現(xiàn)在河南省水利科學(xué)研究院水力學(xué)研究所工作。