任德龍
摘 要:在已建的規(guī)劃區(qū)內(nèi)進(jìn)行項(xiàng)目擴(kuò)建工程,軟土地基的樁基工程施工必須要嚴(yán)格防止因群樁施工的擠土效應(yīng)而造成對臨邊已建構(gòu)筑物或裝置設(shè)施的破壞。寧波萬華二期工程煤氣化區(qū)域樁基工程施工中,由于采取應(yīng)力消散溝和消散孔及沉樁方向、沉樁速率等有效的預(yù)防措施,擠土效應(yīng)得到有效控制,并保證了河邊蒸汽管廊的安全。
關(guān)鍵詞:軟土地基; 擠土效應(yīng); 應(yīng)力消散孔
Soft ground static pressure soil squeezing effect of prestressed pipe pile construction and preventive measures
Ren De-long
( Hualu Engineering Science and Technology Co., Ltd. Xi'an,710065 China )
Abstract: In the planning area has been built, the project expansion project, of pile construction in soft ground due to pile group construction must be strict to prevent soil squeezing effect caused by the destruction of the limb has built a structure or device facilities. Gasification area of pile foundation construction in Ningbo Wanhua two project, due to take stress to dissipate the the ditch, and dissipate hole and pile driving direction, pile driving rate and effective preventive measures, soil compaction effect has been effectively controlled, and ensure the river steam tube of the safety of the Gallery.
Key words: soft ground; soil squeezing effect; stress dissipate hole
2.擠土效應(yīng)介紹
樁基施工中樁尖處土體沖切破壞,擠壓樁周土體形成具有很高孔隙水壓的擾動(dòng)重塑區(qū),其厚度為0.5~1.5倍樁徑。在很強(qiáng)的擠壓作用下,被擾動(dòng)和重塑并變得密實(shí),淺層土?xí)蛏下∑?,要靠消散孔隙水壓力,使緊貼樁身的擾動(dòng)重塑區(qū)產(chǎn)生再固結(jié)而逐漸恢復(fù)土體的抗剪強(qiáng)度后形成在沉樁過程中,相當(dāng)于樁體積的土體向四周排擠,土體破壞使周圍的土受到嚴(yán)重的擾動(dòng),主要表現(xiàn)為徑向位移,樁尖和樁周一定范圍內(nèi)的土體受到不排水剪切以及很大的水平擠壓,樁周土體接近于“非壓縮性”,產(chǎn)生較大的剪切變形,形成具有很高孔隙水壓力的擾動(dòng)重塑區(qū),降低了土的不排水抗剪強(qiáng)度,促使樁周鄰近土體會因不排水剪切而破壞,與樁體積等量的土體在沉樁過程中向樁周發(fā)生較大的側(cè)向位移和隆起。在地面附近的土體是向上隆起,而在地面以下較深層土體,由于覆蓋土層壓力作用不能向上隆起,就向水平方向擠壓。由于群樁施工中的迭加作用,會使已打入樁和鄰近構(gòu)筑物和管線產(chǎn)生較大側(cè)向位移和上浮。樁群越密越大,土的位移也越大,據(jù)寧波地區(qū)樁基施工龍頭企業(yè)——浙江新中源有資料揭示,擠土地面隆起可達(dá)50~60cm,有的甚至達(dá)到70~80cm。這必將影響樁的工程質(zhì)量(變位、上?。?,危及鄰近建筑物和地下管線的安全,破壞性極強(qiáng)。
3.項(xiàng)目情況
煤氣化項(xiàng)目占地面積約8萬平方米,工程造價(jià)約15億人民幣。項(xiàng)目樁基工程采用預(yù)應(yīng)力砼管樁,北面裝置樁基離河邊管廊距離約20m,其中707氣化管樁采用PC-AB600(110)型,單樁設(shè)計(jì)豎向承載力特征值不小于2000KN,以7c層作為樁端持力層,沉樁控制以樁長和最終壓力雙控,樁長約50m∽55m左右,共計(jì)501根,集中施工面積約700m2,擠土估算:管樁進(jìn)土按1/3計(jì)算,該區(qū)域場地?cái)D土為5225m3,管廊北側(cè)是河對管廊周圍土體應(yīng)力有消減作用,這將更加促使管廊周圍土體向河邊位移,河邊蒸汽管廊基礎(chǔ)未打樁,稍有不慎蒸汽管廊將傾覆,后果不堪設(shè)想,如采用鉆孔樁僅707樁基工程將增加費(fèi)用約650萬元,工期將增加60天以上,再加上705/706和672等樁基需增加1500萬左右。
4.采取措施
采用應(yīng)力消散溝和應(yīng)力消散孔,可減少地基淺層軟土的側(cè)向位移和隆起,有利于降低沉樁所引起的超靜孔隙水壓力,從而減少地基深層土體變位。寧波萬華二期工程部分區(qū)域樁基施工雖然采取砂井(應(yīng)力消散孔填碎石或砂)和應(yīng)力消散溝等,但還是導(dǎo)致道路隆起約150mm,道路多處開裂最大達(dá)50mm,周圍管廊偏移達(dá)到130mm。
5.方案
在北側(cè)離樁基約10m左右開挖應(yīng)力消散溝內(nèi)布置應(yīng)力釋放孔,應(yīng)力釋放孔選用泥漿護(hù)壁成孔工藝,孔徑Φ500,深20m,中心間距1500mm,造孔后內(nèi)置通長鋼筋竹籠(用4Φ12作骨架筋,加強(qiáng)箍用1Φ10每隔3m一道,周邊用12根30mm寬竹片用鐵絲綁扎,籠直徑為400mm,具體布置情況見附圖)。根據(jù)應(yīng)力溝內(nèi)定位樣樁將鉆機(jī)水平就位鉆孔,軟土地層:淤泥、粘土、淤泥質(zhì)粘土等層采用三翼刮刀鉆頭正循環(huán)泥漿護(hù)壁回旋鉆進(jìn)成孔,泥漿比重控制在1.2~1.4之間,工程選孔達(dá)到設(shè)計(jì)深度后,將驗(yàn)收合格后的竹籠利用鉆機(jī)副卷揚(yáng)機(jī)吊裝安放入孔內(nèi)。
加強(qiáng)觀測,在混凝土路上做上抬及位移監(jiān)測點(diǎn),間距為15~20m,在鄰周建(構(gòu))筑物上角點(diǎn)處做上標(biāo)高控制點(diǎn)及傾斜變化控制點(diǎn),用紅油漆做出明顯具體的標(biāo)識,進(jìn)行定期的上抬及位移觀測,根據(jù)砼路的材料特性和鄰建物等綜合考慮,以及類似的工程實(shí)例,設(shè)置報(bào)警數(shù)據(jù),上抬量為30mm,水平位移為50mm,傾斜變化不大于20mm,加強(qiáng)觀測由專人負(fù)責(zé),每天觀測一次,當(dāng)出現(xiàn)報(bào)警數(shù)值時(shí)調(diào)整施工速率及采取相應(yīng)的措施,并會同有關(guān)單位共研究處理。
通過樁基施工過程中觀察到,深層淤泥和超靜孔隙水通過應(yīng)力消散孔流出,并及時(shí)清理,采用泥漿護(hù)壁竹籠固孔,這樣應(yīng)力消散孔不易塌孔,竹籠根據(jù)毛細(xì)現(xiàn)象原理可以排水,深層的淤泥土被擾動(dòng)擠壓部分通過應(yīng)力消散孔排出,而填碎石或填砂應(yīng)力消散孔主要起到排水作用,
6.群樁施工節(jié)奏及過程監(jiān)控
6.1沉樁前進(jìn)行探樁
沉樁前清除表面堅(jiān)硬物,促使能更多的讓管內(nèi)進(jìn)土,減少沉樁時(shí)的土體擠壓影響。
控制日成樁速率
在靠近北側(cè)軸線上施工,每天控制在6根樁左右,中間部分在6—8根左右。
6.2 挖設(shè)擠土緩沖溝,溝寬上口3.0m,下口1.5m,深1.5m。
6.3 在北側(cè)防擠溝內(nèi)布置應(yīng)力釋放孔,應(yīng)力釋放孔選用泥漿護(hù)壁成孔工藝,孔徑Φ500,深15m,中心間距1500mm,造孔后內(nèi)置通長鋼筋竹籠(用4Φ12作骨架筋,加強(qiáng)箍用1Φ10每隔3m一道,周邊用12根30mm寬竹片用鐵絲綁扎,籠直徑為400mm,具體布置情況見附圖)
6.4過程監(jiān)控
固定人員對臨邊構(gòu)筑物全過程定期觀測,一般確定為一天兩次監(jiān)測,在施工高峰期可以適時(shí)增加監(jiān)測次數(shù),及時(shí)掌握臨邊構(gòu)筑物的偏移數(shù)值情況。
在混凝土路上做上抬及位移監(jiān)測點(diǎn),間距為15~20m,在鄰周建(構(gòu))筑物上角點(diǎn)處做上標(biāo)高控制點(diǎn)及傾斜變化控制點(diǎn),用紅油漆做出明顯具體的標(biāo)識,進(jìn)行定期的上抬及位移觀測,根據(jù)砼路的材料特性和鄰建物等綜合考慮,以及類似的工程實(shí)例,設(shè)置報(bào)警數(shù)據(jù),上抬量為30mm,水平位移為50mm,傾斜變化不大于20mm,加強(qiáng)觀測由專人負(fù)責(zé),每天觀測一次,當(dāng)出現(xiàn)報(bào)警數(shù)值時(shí)調(diào)整施工速率及采取相應(yīng)的措施,并會同有關(guān)單位共研究處理。
7.應(yīng)力消散孔施工
7.1 挖設(shè)擠土緩沖溝,溝寬上口3.0m,下口1.5m,深1.5m。
7.2 在北側(cè)防擠溝內(nèi)布置應(yīng)力釋放孔,應(yīng)力釋放孔選用泥漿護(hù)壁成孔工藝,孔徑Φ500,深15m,中心間距1500mm。
7.3 造孔后內(nèi)置通長鋼筋竹籠(用4Φ12作骨架筋,加強(qiáng)箍用1Φ10每隔3m一道,周邊用12根30mm寬竹片用鐵絲綁扎,籠直徑為400mm,具體布置情況見附圖)
6.結(jié)語
針對不同的工程施工情況和地質(zhì)條件,采用不同的施工工藝和預(yù)防措施,確保工程質(zhì)量和鄰近建筑物不受破壞。本工程通過上述預(yù)防措施,有效地控制了預(yù)應(yīng)力管樁在沉樁過程中的擠土效應(yīng),并保證河邊蒸汽管廊(基礎(chǔ)未打樁)的安全。整個(gè)項(xiàng)目完成未發(fā)現(xiàn)可見裂縫、位移等現(xiàn)象,預(yù)防措施有效可行。